Open road edges put motorists at risk
Mysuru: The white-topping works on the stretch from Sayyaji Rao Road through Rama Vilas Road to Bogadi Ring Road have left motorists struggling to negotiate several unfinished portions. Residents have urged the authorities to resume work and make the roads safe.
The works were stopped ahead of Dasara and have not been completed, leaving uneven road edges, open trenches and stretches without footpaths. Residents say the unfinished portions have become particularly dangerous for two-wheeler riders and pedestrians. Some commuters have even fallen on the road edges, sustaining injuries.
The State Government had approved converting 12 major
roads into concrete roads. Tenders were floated for 46.08-km at an estimated cost of Rs. 393.85 crore and work had begun on Bogadi Road.
Under the project, a 6-km stretch from Sayyaji Rao Road through Rama Vilas Road, Mysuru Development Authority (MDA) Circle, Kautilya Circle and Kukkarahalli Lake Junction up to Bogadi Ring Road is being converted into a concrete road at a cost of Rs. 34.24 crore.
Work was suspended in September following directions from the District Administration ahead of Dasara. The labourers, many of whom had come from Northern States, returned home during the month-long break, further delaying the project.
The incomplete stretches near Bogadi Ring Road, Kukkarahalli Lake and Yuvaraja’s College Gate have since become a source of concern for road users.
A concerned resident Venkata told Star of Mysore that while portions of the main carriageway on Bogadi-Yuvaraja’s College stretch had been completed, the footpaths and road edges were still left unfinished.
“The unpaved edges are posing a risk to pedestrians and two-wheeler riders, especially at night. Many commuters have fallen and sustained injuries while negotiating these stretches. Also, I fail to understand why white-topping work was taken up on Vishwamanava Double Road before the Bogadi-Yuvaraja’s College stretch was fully completed and made safe for public use,” he said.
The delay has inconvenienced people travelling between Mysuru City and Bogadi every day. Near Kukkarahalli Lake, the newly laid concrete road is about one-and-a-half feet higher than the adjoining footpath. Residents say two-wheeler riders have lost balance and fallen into the side trench at this stretch.
Uneven levels
The road from the University of Mysore’s Crawford Hall to the JLB Road Junction near the MDA office is facing a similar problem, with concrete work completed on only one side.
The work was stopped in the second week of July ahead of Prime Minister Narendra Modi’s visit to inaugurate the Viveka Memorial on Aug. 1. The other side of the road remains unfinished.
Vehicles heading from Crawford Hall to Rama Vilas Road are using the newly laid concrete stretch, while those coming from the opposite direction continue to use the old asphalt road. The two stretches have a level difference of nearly one foot.
Concrete blocks have been placed between the lanes to prevent vehicles from moving across, but residents say the blocks are difficult to spot at night as they have no reflective markings or paint.
Residents have also questioned the removal of trees and protective steel cages along the median of Vishwamanava Double Road.
‘Interlocking work within 15 days’
The concrete road work, which was suspended for a month during Dasara, has now resumed. White-topping work is currently in progress from the Palace West Gate to the Bogadi Ring Road Junction.
UGD pipeline shifting work is underway near Bogadi bridge and MDA Circle. Concrete road work in these stretches will resume once the pipeline relocation is completed. Precautions have been taken to minimise inconvenience to motorists.
Concrete borders have been laid near Harsha Bar Junction. Near Kukkarahalli Lake, the presence of an underground power cable running alongside the road has slowed down the work, as it needs to be shifted safely. Warning signs and cautionary messages have been put up to alert motorists.
Interlocking work along the roadside trenches adjoining the concrete road will be taken up within the next 15 days.
– Mahadevaswamy, AEE, Public Works Department