Bengaluru: The Karnataka High Court (HC) has granted a week’s time for the State Government to decide on the leased out 139.39 acres of land owned by Public Works Department (PWD) in Survey No. 4 and 74 at Kurubarahalli in Mysuru to the Mysore Race Club (MRC). Expressing displeasure over the way how time has been sought on the issue, the HC gave the Government a final chance on the issue. 

The High Court Division Bench comprising Chief Justice Abhay Shreeniwas Oka and Justice S. Vishwajith Shetty yesterday granted a week’s time to the Government while hearing a Public Interest Litigation (PIL) filed by Bengaluru-based advocate S. Umapathi challenging the Government decision to extend the lease of land to the MRC. 

Advocate General of Karnataka Prabhuling K. Navadagi told the Court yesterday that the Government was re-examining the possibilities of taking back the land leased out to the MRC and to take an official position, the Government needed more time. 

To this, the High Court Bench said that when the matter came up for hearing on Mar. 30, a week’s time was granted so that a final decision could be taken. The Bench pointed out that before the Mar. 30 hearing it had asked the submission of file noting and all the other relevant documents that enabled the State Cabinet to take a decision on extending the lease with retrospective effect from July 1, 2016 till July 31, 2046 on a rent of merely 2 percent gross annual income of MRC. 

The Bench questioned the Advocate General on the time limit and also took objection to the persistent demand of time by the Government to settle the issue and report to the Court on what measures have been initiated following the Court observations. 

The Bench asked the Advocate General that in the last hearing, while accepting that the Government needed a week’s time to relook into the issue, granted time till Apr. 7 but the Government had not placed its decision before the Court. The two-judge Bench then granted time till Apr. 15 for the Government to file its reply and posted the case to that day. 

Advocate Umapathi filed the PIL challenging the Government’s decision. In his petition, Umapathi said that prime public land was leased out to MRC in 1970. The lease was renewed from time to time                                                                       and eventually expired in 2016. He claimed that lease was contrary to the provision of the Karnataka Land Revenue Rules and resulted in huge loss to the State exchequer.

This post was published on April 8, 2021 6:39 pm