Rs. 9.75 crore campus lacks basic amenities
- No water, power or proper classrooms at new campus
- No conducive learning atmosphere, say students, faculty
Mysuru: The sprawling new campus of Karnataka State Dr. Gangubai Hangal Music and Performing Arts University at Nadanahalli is virtually deserted. The eight learning cottages are empty and the campus, which was expected to be a centre for music and performing arts, has fallen silent.
Nearly 16 years after its establishment, the University finally got a permanent campus. But the facility, on the outskirts of Mysuru at Nadanahalli (Sardar Vallabhbhai Patel Nagar), has been left largely unused just months after academic activities began there.
Established at Lakshmipuram in 2008, the University was shifted to the 5.5-acre campus after years of functioning without a permanent home.
The campus was built at a cost of Rs.9.75 crore on land allotted by the Mysuru Development Authority (MDA). It has administrative offices, cottage-style classrooms and a library. Academic activities began there on July 25, 2025.
However, students and staff soon faced problems due to the lack of basic facilities. The University has now moved back to its old heritage building in Lakshmipuram, which was also proposed to be developed into a museum dedicated to Dr. Gangubai Hangal.
The new premises remain largely deserted, with shrubs and wild growth around the administrative block and classrooms. A security guard is among the few people seen there.
Basic facilities missing
Students and faculty members, speaking on condition of anonymity, told Star of Mysore that the absence of basic facilities had made it difficult to conduct classes and other activities.
They said the girls’ restroom did not provide adequate privacy. There were also problems with water supply and drinking water, while the campus lacked a proper electricity connection.
Dust, poor transport facilities and the distance from the city made matters worse. Students also complained about stray dogs, snakes and scorpions on the premises.
Cracks in building, other problems
Apart from the Vice-Chancellor’s office, most facilities were not functioning satisfactorily. Cracks have appeared on the walls of the administrative building, which was completed less than a year ago and patchwork repairs have been carried out.
“The roofing sheets over the parking area were blown away by strong winds. The eight cottage-style classrooms are too small to accommodate students comfortably and also leak during the rainy season,” a lecturer said.
He added that there was no proper space for Bharatanatyam practice and other performing arts activities.
Questions over construction quality
Critics have questioned the speed at which the project was completed. Construction began in February 2025 and was reportedly finished within five to six months.
They alleged that plastering and painting were carried out in quick succession, raising doubts about the quality of work.
They also felt that conventional classroom blocks would have been more suitable than the cottage-style structures. The Gurukula-style concept, they said, has not met the Music University’s actual needs.
“A female student lost her gold chain in a theft on the campus. The incident, along with the isolated location, has added to our concerns about safety. The distance from the city has also affected admissions,” a student said.
With the problems yet to be addressed, the University continues to function from its old building in Lakshmipuram. There is no clear timeline for the resumption of academic activities at Nadanahalli.
The new campus lacks several basic amenities, including drinking water facilities. Each classroom accommodates around 15 to 20 students and the cottage-style classrooms are too small. Transport connectivity is also inadequate. Cracks that appeared in the walls have been identified and patchwork has been carried out. Earlier, there was a proposal to construct a hostel building. However, it was later decided that classroom blocks should be prioritised instead. A letter has been sent to the executing agency seeking modification of the project. Construction work is expected to begin shortly. Academic activities at the new campus will resume after the new classroom buildings are completed.
—Prof. K. Ramakrishnaiah, Vice-Chancellor, Karnataka State Dr. Gangubai Hangal Music and Performing Arts University
This post was published on November 21, 2026 7:30 pm