Railway Board has permitted to take up the Pre Non-Interlocked working for 17 days from Feb. 10 to Feb. 26, 2017 and Non-Interlocked working for 2 days from Feb. 27 to Feb. 28, 2017 at Londa Junction for commissioning of Londa stage-1 work in connection with doubling of Hubballi-Londa-Vasco-da-gama sections.
As such, Train No. 51431/ 51432, Miraj-Londa-Miraj Passenger will be partially cancelled between Londa-Gunji-Londa for 11 days from Feb. 18 to Feb. 28; Train No. 51405/51406, Miraj-Castlerock-Miraj Passenger will be partially cancelled between Belagavi-Castlerock-Belagavi for 11 days from Feb. 18 to Feb. 28.