Mysuru: The pending 1.7 kilometre stretch of track doubling between Bengaluru-Mysuru at Srirangapatna has been commissioned for traffic. With the commissioning of the track yesterday, the entire 138.3 kms stretch between the two cities is complete. For now, trains with diesel engines are plying both ways but once the electrification between Yeliyur near Mandya and…
Double Railway track at Srirangapatna to be commissioned on Nov. 19
November 16, 2017Mysuru: After the Commissioner of Railway Safety (CRS) approved train operations on the much-delayed track-doubling work at Srirangapatna, the newly-laid 1.7-km stretch will be commissioned on Nov. 19. It may be recalled here that the statutory inspection of the pending 1.7 km stretch of Railway line near Srirangapatna — taken up as part of track-doubling…