Kodagu’s first flyover opens for public use
Feature Articles, Top Stories

Kodagu’s first flyover opens for public use

May 6, 2024

Now, travelling to holy places Talacauvery and Bhagamandala becomes hassle-free

In what is considered a significant relief for travellers and residents, commuting to holy places like Talacauvery and Bhagamandala will now be hassle-free as the authorities have opened the Bhagamandala flyover — Kodagu’s first flyover project — for public use.

The State Government had allocated Rs. 28 crore for the project, which was executed by Cauvery Neeravari Nigam Limited (CNNL). With the completion of the flyover, villagers surrounding Bhagamandala and Talacauvery can now travel with ease, even during heavy rainfall, without fearing floods. However, there has been no official inauguration due to the Model Code of Conduct, which  remains in effect until June 4.

No fear of floods

During the rainy season, Brahmagiri Hills, Talacauvery, Korangala, Cherangala, Bhagamandala and surrounding areas experience heavy rainfall, leading to an overflow of water at Triveni Sangama, the confluence of the Cauvery, Kannike and Sujyothi rivers. 

This overflow often disrupts vehicular movement on Madikeri-Bhagamandala-Talacauvery and Bhagamandala-Ayyangeri-Napoklu roads. Additionally, heavy rains sometimes result in the isolation of Bhagamandala, effectively turning the town into an island for many days. 

The flooded roads render them impassable for vehicles, causing significant inconvenience for residents who struggle to access essential items and groceries. School children are unable to attend classes due to the flooded roads, exacerbating the situation. The completion of the flyover has alleviated these challenges, bringing much-needed relief to the residents of Bhagamandala and surrounding areas.

880 metres-long flyover

The newly-constructed flyover serves as a vital link between the Bhagamandala entrance gate and Talacauvery road, providing connectivity to Napoklu as well. Spanning 880 metres in length, it comprises 36 pillars and includes a 200-metre connecting road with underground drainage (UGD) facilities. 

READ ALSO  Rescue operations gain momentum in flood-ravaged Kodagu

Designed to accommodate vehicles weighing over 60 tonnes, the authorities have set a speed limit of 40 kmph. Streetlights have been installed along with rainwater drainage pipelines and the painting works have been completed.

CAUSES FOR DELAY                                                          

Despite receiving approval from the Siddaramaiah-led Government in 2018, the project faced delays due to challenges such as land acquisition, relocation of electric poles and tree removal by the Forest Department. The floods and COVID-19 lockdown further contributed to the sluggish progress of the project.

The flyover construction has been finished ahead of this rainy season. Vehicles of various types and sizes can now traverse the flyover smoothly, ensuring a hassle-free journey for those  heading towards Bhagamandala-Talacauvery and Bhagamandala-Napoklu, said Harinarayana, Flyover Project Director.

ABOUT

Mysuru’s favorite and largest circulated English evening daily has kept the citizens of Mysuru informed and entertained since 1978. Over the past 45 years, Star of Mysore has been the newspaper that Mysureans reach for every evening to know about the happenings in Mysuru city. The newspaper has feature rich articles and dedicated pages targeted at readers across the demographic spectrum of Mysuru city. With a readership of over 2,50,000 Star of Mysore has been the best connection between it’s readers and their leaders; between advertisers and customers; between Mysuru and Mysureans.

CONTACT

Academy News Papers Private Limited, Publishers, Star of Mysore & Mysuru Mithra, 15-C, Industrial ‘A’ Layout, Bannimantap, Mysuru-570015. Phone no. – 0821 249 6520

To advertise on Star of Mysore, email us at

Online Edition: [email protected]
Print Editon: [email protected]
For News/Press Release: [email protected]