Additional ramp being built; project cost escalates from Rs. 10.86 crore to Rs. 23.28 crore Mysore/Mysuru: The Town Hall parking facility in the heart of the city is turning out to be Hamlet’s Ghost of our time as it is only during Dasara that the people in power think of the parking facility as Hamlet’s…
One more deadline for Town Hall Multi-level Parking facility
February 9, 2021Mysuru District Minister asks officials to complete the works in six months Mysore/Mysuru: The much-touted Town Hall Multi-level Parking facility has got one more deadline — August 2021 — this time by Mysuru District Minister S.T. Somashekar. The ambitious project began on April 11, 2011 and the deadline of 2012 is not met and it…
Not Before Dasara: Town Hall Parking, Irwin Road Widening
August 19, 2019Timeline of Town Hall Parking Project • Project begins on April 11, 2011 • Project deadline 2012 not met • Project delayed every year since 2012 • 2019, 8 years on, project still in limbo • Now, MCC wants to relaunch pending works, seeks Rs.5 crore Mysuru: Just 40 days for Naada Habba to begin…
Fleecing at Town Hall Parking Facility: MCC cancels parking tender contract
November 23, 2018Car parking back at Kote Anjaneyaswamy Temple premises Mysuru: The Mysuru City Corporation (MCC) has cancelled the parking tender contract of Town Hall multi-level pay-and-park facility. Even the parking of vehicles there has been stopped following complaints of fleecing of motorists by the contractor to recover his tender costs. It may be recalled here that…