Restoring Chamundi Hill Landslides: Eight months on, PWD awaits fund clearance
News, Top Stories

Restoring Chamundi Hill Landslides: Eight months on, PWD awaits fund clearance

June 17, 2022

Fresh cracks appear on road owing to heavy rains

Mysore/Mysuru: Nearly eight months after the fourth massive landslide atop Chamundi Hill, the Public Works Department (PWD), which has the responsibility of reconstructing the collapsed portion and building a retaining wall to prevent further damages, is awaiting fund clearance from the      Finance Department.

A budget of Rs. 9.96 crore has been allocated and tenders have been issued. But the proposal is pending before the Finance Department which is yet to give green signal to the project. PWD Assistant Executive Engineer Raju told Star of Mysore this morning that the proposal is pending before the Government.

“Approval is likely to come in a fortnight or so and we will start the works soon,” he said.

By the time PWD begins work, the monsoon will set in and the Department has no answers on how it is going to take up works amidst rains. The first landslide occurred on the night of Oct. 20, 2021 and subsequently, three more landslips occurred, the last one being on Nov. 18.  These landslides have resulted in forming of huge craters with the old retaining wall crashing, forming a deep muddy slope.

After the first or second collapse, the officials stated that the rain should stop to take up repair works. However, even after the rain gave a break for over two months, the works did not start as the Finance Department did not give approval. Now if the works start amidst rain, how the officials will ensure quality works is a million-dollar question.

Meanwhile, even before the onset of the monsoon, the road leading to the Nandi Statue atop the Hill has developed new cracks in some places, triggering fear of more landslides. Assistant Executive Engineer Raju said that all the repairs will be taken up in a comprehensive manner. “We cannot do patch work here and as it is raining heavily, cracks do occur as water seeps through the soil continuously. The rains have to stop completely for the works to begin,” he added. After the initial landslides, scientists from the Indian Institute of Science (IISc) submitted a report after studying the pattern of the landslides, soil and other factors.

READ ALSO  Rahul performs ‘Sankalpa’at Chamundi Temple

IISc scientists suggested ‘reinforced earth steepened slope structure wall’ technique to restore the damaged areas. The scientists studied the landslide pattern and took samples from faults, joints and bedding surfaces, which are contact points between rock and soil and contribute to landslides.

ONE COMMENT ON THIS POST To “Restoring Chamundi Hill Landslides: Eight months on, PWD awaits fund clearance”

  1. Sanjay Kini says:

    In Africa to prevent floods on hills Bamboo is planted on hill slopes. Why not plant Bamboo next to the retaining walls to prevent soil erosion. If any botanist could comment for this post.

ABOUT

Mysuru’s favorite and largest circulated English evening daily has kept the citizens of Mysuru informed and entertained since 1978. Over the past 45 years, Star of Mysore has been the newspaper that Mysureans reach for every evening to know about the happenings in Mysuru city. The newspaper has feature rich articles and dedicated pages targeted at readers across the demographic spectrum of Mysuru city. With a readership of over 2,50,000 Star of Mysore has been the best connection between it’s readers and their leaders; between advertisers and customers; between Mysuru and Mysureans.

CONTACT

Academy News Papers Private Limited, Publishers, Star of Mysore & Mysuru Mithra, 15-C, Industrial ‘A’ Layout, Bannimantap, Mysuru-570015. Phone no. – 0821 249 6520

To advertise on Star of Mysore, email us at

Online Edition: [email protected]
Print Editon: [email protected]
For News/Press Release: [email protected]