Bengaluru: The recent rain and the lake breach along the work-in-progress 10-lane Mysuru-Bengaluru Economic Corridor (Expressway) has made the authorities realise that there is still plenty of work to be done on the road front to control the flow of water. The authorities have conceded that it will take a minimum of six months to…
Status of 10-lane Mysuru-Bengaluru Highway: Main carriageway to open in October this year: MP
July 22, 2022Mysore/Mysuru: Amidst reports that the 10-lane Mysuru-Bengaluru Economic Corridor (Expressway) will not be open anytime soon, Mysuru-Kodagu MP Pratap Simha has clarified that the main carriageway of the Expressway will be open to traffic by October this year. During the Dasara High-Powered Committee meeting in Bengaluru on July 19, Chief Minister Basavaraj Bommai told reporters…
Mysuru-Bengaluru 10-lane Economic Corridor: MP urges NHAI to solve safety issues
May 12, 2022Certain landowners at Ramanagara were holding up construction work Mysore/Mysuru: Highlighting the safety and aesthetics of the ongoing 10-lane Mysuru-Bengaluru Economic Corridor, Mysuru-Kodagu MP Pratap Simha has urged National Highways Authority of India (NHAI) to take immediate measures to pave the earthen shoulder with suitable impermeable material like concrete. Meeting NHAI Chairperson Alka Upadhyaya recently,…
Mysuru-Bengaluru 10-lane Economic Corridor: Proper entry, exit points needed for 5 bypasses
December 16, 2021Call to expedite grade separator near Columbia Asia Hospital Junction Mysore/Mysuru: Meeting Union Minister Nitin Gadkari in New Delhi yesterday, MP Pratap Simha also requested the upgradation of the access controlled 10-lane Mysuru-Bengaluru Economic Corridor with proper entry and exit points for all five bypasses to six towns. Also, to avoid median crossover accidents, Jersey…
Mysuru-Bengaluru 10-Lane Economic Corridor: Rs. 8,066 crore project cost to exceed by Rs. 700 crore
September 6, 2021Mysore/Mysuru: The construction of 10-lane Mysuru-Bengaluru Economic Corridor is in full swing and it is scheduled to be completed by October 2022. But the estimated cost of Rs. 8,066 crore might exceed by another Rs. 700 crore. The corridor comprises a six-lane access-controlled carriageway for traffic to move at a high speed and a two-lane…
Mysuru-Bengaluru 10-lane Economic Corridor: ’90-minute journey from Oct. 2022′
August 13, 2021Tweets Minister for Road Transport and Highways Nitin Gadkari Mysore/Mysuru: The construction of 10-lane Mysuru-Bengaluru Economic Corridor is in full swing and photos of the project have been tweeted by Minister for Road Transport and Highways Nitin Gadkari. Taking to the micro-blogging site, the Minister gave a glimpse of the project to commuters and said…
Mysuru-Bengaluru Economic Corridor: 55 percent of works complete; to be ready by Feb. 2022
February 5, 2021Bengaluru: Over 55 percent of the works of Mysuru-Bengaluru Economic Corridor project have been completed and the project will be dedicated to the nation in February 2022, announced Deputy Chief Minister Govind M. Karjol who also holds the Public Works Department portfolio. Making an announcement in this regard in the Legislative Council on Wednesday, the…