Construction of Chamundi Hill retaining wall: 10 months on, 40 percent work over; 3 more months needed
News

Construction of Chamundi Hill retaining wall: 10 months on, 40 percent work over; 3 more months needed

June 6, 2023

New technology of fixing retaining wall to Hill’s rocky structure to prevent landslides

Mysore/Mysuru: Works on constructing a retaining wall to restore the portions of the Nandi Statue Road atop Chamundi Hill that witnessed a series of landslides is still a work-in-progress project even after 10 months and till now, only 40 percent has been completed.

As all iron and steel fabrication and precast concrete materials are ready with only fixing part pending, engineers told Star of Mysore this morning that they need three more months to complete the project.

The work on the retaining wall began in August 2022 after the then Government released Rs. 10 crore and till December last year, heavy rains hampered the construction. The earthworks have now been completed and a 30-ft trench has been dug up to accommodate the huge retaining wall. The foundation for the wall has been laid and the structure has been raised to the top,  PWD Executive Engineer Raju told Star of Mysore this morning.

Extensive damage has been caused between the View Point and Nandi Statue and the damages extend up to 400 metres. All the materials required for the civil works like cement and iron have been kept ready and we need to fix it now. We are using a new technique where the massive retaining wall is fixed to the Chamundi Hill’s rocky surface with the help of grooves where iron rods are inserted and they are then grouted into place. This will prevent future landslides,” Raju explained.

READ ALSO  More laddus for devotees

The retaining wall needs to be built on level ground and to avoid pressure, engineers have excavated deep enough (up to 30 ft) for the base material and one course of wall material. This structure is then fixed to the rocks (with tension-resisting steel rods) so that it will stay put even in adverse conditions and heavy rains,” PWD EE Raju added.

The retaining wall is being constructed based on the suggestions of scientists from the Indian Institute of Science (IISc.), Bengaluru, who have submitted a detailed report on the landslides after soil testing and other studies and the methodology of constructing the retaining wall. Landslides have taken place at two locations a couple of times on the Nandi Statue Road. Once the work of this retaining wall is completed, the work on the other portion will have to be taken up and a fresh estimate has to be prepared for the Government to sanction money.

Ever since the landslides, the road to Nandi Statue has been closed for traffic while the other roads leading up the Hill are open.

2 COMMENTS ON THIS POST To “Construction of Chamundi Hill retaining wall: 10 months on, 40 percent work over; 3 more months needed”

  1. Sanjay Kini says:

    Make Chamundi hill road a toll road let government earn revenue to get these repair works done for now and in the future.let residents of the hill be given pass for their vehicles and let the rest of the vehicles pay toll to use the hill road.let tourist buses be charged INR 1000/- toll so only tourists who really want to go to the temple paying toll will go and it will reduce the load on the hill.

  2. Howdy, Modi! says:

    Keep all visitors to the Hill off the road. They should all take steps to climb to reach the Temple.
    Otherwise, this Hill will crumble into a big pile of rubble within a few years. It is tourism which has endangered this Hill and is destroying Mysore,.
    Mysore does not need tourism as it is well developed with industries.

ABOUT

Mysuru’s favorite and largest circulated English evening daily has kept the citizens of Mysuru informed and entertained since 1978. Over the past 45 years, Star of Mysore has been the newspaper that Mysureans reach for every evening to know about the happenings in Mysuru city. The newspaper has feature rich articles and dedicated pages targeted at readers across the demographic spectrum of Mysuru city. With a readership of over 2,50,000 Star of Mysore has been the best connection between it’s readers and their leaders; between advertisers and customers; between Mysuru and Mysureans.

CONTACT

Academy News Papers Private Limited, Publishers, Star of Mysore & Mysuru Mithra, 15-C, Industrial ‘A’ Layout, Bannimantap, Mysuru-570015. Phone no. – 0821 249 6520

To advertise on Star of Mysore, email us at

Online Edition: [email protected]
Print Editon: [email protected]
For News/Press Release: [email protected]