SWR completes maintenance works during COVID lockdown
COVID-19, News

SWR completes maintenance works during COVID lockdown

June 19, 2020

Three Level Crossing Gates were eliminated on Mysuru-Hassan section by constructing low height subways

Mysore/Mysuru: The suspension of regular train services due to COVID-19 enabled the South Western Railway (SWR) to complete the safety and infrastructure works, besides taking up maintenance of tracks and other works across the zone.

This includes monsoon preparedness in the Ghat sections, closing of a few unmanned Level Crossing Gates and eliminating manned Level Crossing Gates by constructing Road Under Bridges (RUBs).

According to an SWR statement, all planned safety works in the Ghat section between Castle Rock and Kulem section of Hubballi division are nearing completion. There was no disruption of train services as only a few special trains operate at present and this also did not lead to staggering of works, it added.

Between Castle Rock and Kulem, 2,000 sleepers were removed from side drains to facilitate water flow during monsoon and prevent track flooding, which could endanger safety. Repair of eight minor bridges on the Ghat section between Londa-Miraj and Londa and Vasco-da-gama section was also taken up and the bridges are now ready for safe running of trains.

In Mysuru division, three Level Crossing Gates were eliminated on the Mysuru-Hassan section by constructing low height subways. An official statement said the construction entailed insertion of precast boxes under the track and were completed in a matter of hours, which in normal times, would have led to cancellation or regulation of a number of passenger trains.

There are 311 manned Level Crossing Gates in Mysuru Division, of which 30 were eliminated last year and 16 were targeted for elimination by construction of subways this year, it added. According to the statement, a canal crossing work between Ajjampura and Shivani Stations on Tumakuru-Hubballi line was underway.

READ ALSO  COVID Warrior dies of Coronavirus

It was earlier planned with daily blocking of track for a few hours and the work was to be staggered over a period of 90 days. But taking advantage of the lockdown, it has been planned for early completion.

”This project would facilitate the supply of water from Bhadra River to drought-hit regions of 

Chitradurga. The Mysuru Division has taken up the project as a challenge and work is in progress day and night,” it added.

Track maintenance and monitoring received top priority and the Oscillation Monitoring System (OMS), which detects geometrical defects in the track, was run at a regular interval of 15 days. This entailed covering a distance of 6,268 km during the lockdown period and maintenance works were taken up based on these results, as per the defined protocols.

Similarly, Ultrasonic Flaw Detection System, which is used to detect the internal flaws in the rail, was carried out over 321.85km length of track, the statement added.

ABOUT

Mysuru’s favorite and largest circulated English evening daily has kept the citizens of Mysuru informed and entertained since 1978. Over the past 45 years, Star of Mysore has been the newspaper that Mysureans reach for every evening to know about the happenings in Mysuru city. The newspaper has feature rich articles and dedicated pages targeted at readers across the demographic spectrum of Mysuru city. With a readership of over 2,50,000 Star of Mysore has been the best connection between it’s readers and their leaders; between advertisers and customers; between Mysuru and Mysureans.

CONTACT

Academy News Papers Private Limited, Publishers, Star of Mysore & Mysuru Mithra, 15-C, Industrial ‘A’ Layout, Bannimantap, Mysuru-570015. Phone no. – 0821 249 6520

To advertise on Star of Mysore, email us at

Online Edition: [email protected]
Print Editon: [email protected]
For News/Press Release: [email protected]